|
23 October -2024 |
B and C block
Block B - gas meters were installed, ceramic granite was laid on the entrance hall and balcony, a fire system was made, the entrance doors of the apartment are being installed; Block C - facade finishing works are being completed, roof covering is finished. The stretch floor is being laid. |
Gallery
|
Gallery |
|
|
|
09 September -2024 |
Internal works
Block A - completed; Block B - finishing of the facade and decoration of the entrance was completed, an elevator was installed; Block C - interior partitions are being plastered and the exterior facade is being finished, an elevator has been installed. |
Gallery
|
Gallery |
|
|
|
15 July -2024 |
Elevator Installation
Elevator installation works are underway in Avchala. |
Gallery
|
Gallery |
|
|
|
27 June -2024 |
Repair Works
Residents of Block A of Avchala have started internal repair work. |
Gallery
|
Gallery |
|
|
|
30 April -2024 |
Internal workIn block A - the installation of railings, and doors, and the work of removing the internal partitions has been completed. Balconies and hallways are finished with ceramic granite; In block B - in the apartments, the removal of internal partitions, and the installation of railings on balconies and stairwells was completed; In block C - the monolith work is completed and the internal partitions are in progress. |
Gallery
|
Gallery |
|
|
|
22 April -2024 |
Accommodation
In Avchala, the internal and external works have been completed, the tenants who have been covered for the full cost of the apartment are starting the repair work. |
Gallery
|
Gallery |
|
|
|
03 April -2024 |
Installation of doorsIn Avchala, the iron doors to the apartments are being installed, as well as the hallways and balconies. At the same time, facade painting works. |
Gallery
|
Gallery |
|
|
|
25 January -2024 |
Internal workIn block A - the installation of doors and windows and the railings of the entrance stairs have been completed. Plastering works of the facade are in progress. In block B - the slab of the eighth floor is being poured. The work of removing the internal partitions including the sixth floor has been completed. In Block C - the slab of the fourth floor is being laid. |
Gallery
|
Gallery |
|
|
|
14 December -2023 |
Internal plasteringIn Avchala block A, internal plastering works are underway. The entrance iron doors for the apartments, which are made of stone, have also arrived. |
Gallery
|
Gallery |
|
|
|
29 October -2023 |
OverlappingIn the A sector, there are: Roofing works; Door-window insertion (including 3 floors); Installation of sewer pipes. In the B sector, there is - Placing the 5th-floor slab and removing internal partitions. In sector C, foundation pouring has been completed.. |
Gallery
|
Gallery |
|
|
|
25 August -2023 |
MonolithThe construction of the monolith of block A in Avchala has been completed. In Block B, the floor of the 4th floor has been poured, and the partitions of the 2nd and 3rd floors have also been built. |
Gallery
|
Gallery |
|
|
|
29 June -2023 |
7th FloorThe laying of the slab of the 7th floor on block А has been completed. Arrangement of slab molds for the 3rd floor on block B is in progress. |
Gallery
|
Gallery |
|
|
|
02 June -2023 |
6th FloorIn Avchala, in sector A, the floor of the 6th floor was laid, and the almatur needed for the current convoys was poured. Also, in agreement with the tenants, the construction of internal partitions was completed on the 4th floor, and the construction of external partitions on the 5th floor is underway. |
Gallery
|
Gallery |
|
|
|
05 May -2023 |
5th floorIn Avchala, the 5th floor tile was poured on block А. On the built floors, the apartments are being opened and walls are being erected on the facade. And in block B, column diaphragms were arranged on the 2nd floor. |
Gallery
|
Gallery |
|
|
|
03 April -2023 |
ColumnsIn Avchala Block A the outer and inner partitions of the commercial floor were built. Columns of the fourth floor were poured. In Block B, the commercial floor columns have been poured and preparations are underway to pour the second floor slab. |
Gallery
|
Gallery |
|
|
|
15 March -2023 |
3rd Floor tileColumns of the second floor, elevator shaft and stairs were installed in Avchala sector A. Preparatory work for the third floor slab was also carried out and the slab was poured. Almatura was spun for the columns of the commercial floor in sector B, and the elevator shaft was prepared for pouring concrete. |
Gallery
|
Gallery |
|
|
|
20 February -2023 |
The craneTower crane, СОMANSA NT 40100, is being installed. Start of construction of Block B planned in March in parallel mode. |
Gallery
|
Gallery |
|
|
|
10 February -2023 |
2nd FloorThe concrete pouring of the roof of Block A commercial floor has been completed. Next step erection and installation of the rebars frames on the Second living floor. |
Gallery
|
Gallery |
|
|
|
24 January -2023 |
Commercial roofingRoofing slabs of the commercial floor of Block A are in progress. |
Gallery
|
Gallery |
|
|
|
20 December -2022 |
ColumnsIn block A, the columns and walls of the commercial floor were poured. In block B, the construction of the columns of the commercial floor is in progress. |
Gallery
|
Gallery |
|
|
|
01 November -2022 |
Commercial floorIn block A, the laying of the slab of the commercial floor is in progress, and in block B, the laying of the column of the 0th floor is in progress. |
Gallery
|
Gallery |
|
|
|
10 October -2022 |
Block AThe walls of the underground floor of block A were poured. In the next week, the waterproofing of the walls will be arranged and the earth will be backfilled into the foundation. |
Gallery
|
Gallery |
|
|
|
04 October -2022 |
WallsFoundation walls and columns are made on block A Reinforced concrete slab, reinforced concrete basement walls and diaphragms are poured on block B. |
Gallery
|
Gallery |
|
|
|
22 September -2022 |
Underground FloorThe foundation slab of block A is poured. on 440m2. The walls of the underground floor of Block B are poured. By the end of the month, it is planned to pour the walls of the underground floor of block A and waterproof the outer perimeter of its walls. |
Gallery
|
Gallery |
|
|
|
01 September -2022 |
walls and columnsIn block A, the foundation slab is being prepared, and in block B, reinforced concrete walls and columns are being built. |
Gallery
|
Gallery |
|
|
|
16 August -2022 |
The foundation laidThe foundation of block B was laid. 80 cm thick at the -3.00 mark. We are starting to arrange the walls and roofing structures of the underground floor. as well as reinforcement of the foundation of block A. |
Gallery
|
Gallery |
|
|
|
03 August -2022 |
FoundationAt this stage, the reinforcement of the foundation slab is underway. |
Gallery
|
Gallery |
|
|
|
16 July -2022 |
Land worksConstruction has started in Avchala, and at this stage, land is being cut for the foundation. |
Gallery
|
Gallery |
|
|
|
22 June -2022 |
PreparationThe surrounding area is being rehabilitated and preparations are underway for the ground works. |
Gallery
|
Gallery |
|