Construction Process

01
23 October -2024

B and C block

Block B - gas meters were installed, ceramic granite was laid on the entrance hall and balcony, a fire system was made, the entrance doors of the apartment are being installed;

Block C - facade finishing works are being completed, roof covering is finished. The stretch floor is being laid.

02
09 September -2024

Internal works

Block A - completed;

Block B - finishing of the facade and decoration of the entrance was completed, an elevator was installed;

Block C - interior partitions are being plastered and the exterior facade is being finished, an elevator has been installed.

03
15 July -2024

Elevator Installation

Elevator installation works are underway in Avchala.

04
27 June -2024

Repair Works

Residents of Block A of Avchala have started internal repair work.

05
30 April -2024

Internal work

In block A - the installation of railings, and doors, and the work of removing the internal partitions has been completed. Balconies and hallways are finished with ceramic granite; In block B - in the apartments, the removal of internal partitions, and the installation of railings on balconies and stairwells was completed; In block C - the monolith work is completed and the internal partitions are in progress.

06
22 April -2024

Accommodation

In Avchala, the internal and external works have been completed, the tenants who have been covered for the full cost of the apartment are starting the repair work.

07
03 April -2024

Installation of doors

In Avchala, the iron doors to the apartments are being installed, as well as the hallways and balconies. At the same time, facade painting works.

08
25 January -2024

Internal work

In block A - the installation of doors and windows and the railings of the entrance stairs have been completed. Plastering works of the facade are in progress. In block B - the slab of the eighth floor is being poured. The work of removing the internal partitions including the sixth floor has been completed. In Block C - the slab of the fourth floor is being laid.

09
14 December -2023

Internal plastering

In Avchala block A, internal plastering works are underway. The entrance iron doors for the apartments, which are made of stone, have also arrived.

10
29 October -2023

Overlapping

In the A sector, there are: Roofing works; Door-window insertion (including 3 floors); Installation of sewer pipes. In the B sector, there is - Placing the 5th-floor slab and removing internal partitions. In sector C, foundation pouring has been completed..

11
25 August -2023

Monolith

The construction of the monolith of block A in Avchala has been completed. In Block B, the floor of the 4th floor has been poured, and the partitions of the 2nd and 3rd floors have also been built.

12
29 June -2023

7th Floor

The laying of the slab of the 7th floor on block А has been completed. Arrangement of slab molds for the 3rd floor on block B is in progress.

13
02 June -2023

6th Floor

In Avchala, in sector A, the floor of the 6th floor was laid, and the almatur needed for the current convoys was poured. Also, in agreement with the tenants, the construction of internal partitions was completed on the 4th floor, and the construction of external partitions on the 5th floor is underway.

14
05 May -2023

5th floor

In Avchala, the 5th floor tile was poured on block А. On the built floors, the apartments are being opened and walls are being erected on the facade. And in block B, column diaphragms were arranged on the 2nd floor.

15
03 April -2023

Columns

In Avchala Block A the outer and inner partitions of the commercial floor were built. Columns of the fourth floor were poured. In Block B, the commercial floor columns have been poured and preparations are underway to pour the second floor slab.

16
15 March -2023

3rd Floor tile

Columns of the second floor, elevator shaft and stairs were installed in Avchala sector A. Preparatory work for the third floor slab was also carried out and the slab was poured. Almatura was spun for the columns of the commercial floor in sector B, and the elevator shaft was prepared for pouring concrete.

17
20 February -2023

The crane

Tower crane, СОMANSA NT 40100, is being installed. Start of construction of Block B planned in March in parallel mode.

18
10 February -2023

2nd Floor

The concrete pouring of the roof of Block A commercial floor has been completed. Next step erection and installation of the rebars frames on the Second living floor.

19
24 January -2023

Commercial roofing

Roofing slabs of the commercial floor of Block A are in progress.

20
20 December -2022

Columns

In block A, the columns and walls of the commercial floor were poured. In block B, the construction of the columns of the commercial floor is in progress.

21
01 November -2022

Commercial floor

In block A, the laying of the slab of the commercial floor is in progress, and in block B, the laying of the column of the 0th floor is in progress.

22
10 October -2022

Block A

The walls of the underground floor of block A were poured. In the next week, the waterproofing of the walls will be arranged and the earth will be backfilled into the foundation.

23
04 October -2022

Walls

Foundation walls and columns are made on block A Reinforced concrete slab, reinforced concrete basement walls and diaphragms are poured on block B.

24
22 September -2022

Underground Floor

The foundation slab of block A is poured. on 440m2. The walls of the underground floor of Block B are poured. By the end of the month, it is planned to pour the walls of the underground floor of block A and waterproof the outer perimeter of its walls.

25
01 September -2022

walls and columns

In block A, the foundation slab is being prepared, and in block B, reinforced concrete walls and columns are being built.

26
16 August -2022

The foundation laid

The foundation of block B was laid. 80 cm thick at the -3.00 mark. We are starting to arrange the walls and roofing structures of the underground floor. as well as reinforcement of the foundation of block A.

27
03 August -2022

Foundation

At this stage, the reinforcement of the foundation slab is underway.

28
16 July -2022

Land works

Construction has started in Avchala, and at this stage, land is being cut for the foundation.

29
22 June -2022

Preparation

The surrounding area is being rehabilitated and preparations are underway for the ground works.