Construction Process

01
05 November -2024

The first layer of the foundation

Block A - removal of internal and neighboring partitions on the 8th and 9th floors is in progress;

Block B - the foundation was placed on a rock mass, which is distinguished by its exceptional strength and seismic resistance. The first layer of the foundation has been poured, the reinforcement is being tied to pour the 2nd slab of the foundation.

02
23 October -2024

9th floor

Block A - the construction of the block on the 9th floor is in progress;

Block B - ground cutting works are being completed.

03
09 October -2024

8th and 9th floor

А ბლოკი - მიმდინარეობს მე-8 და მე-9 სართულის სამეზობლო ტიხრების ამოყვანის სამუშაოები;

B ბლოკი - მიმდინარეობს კატლავანის ამოღების სამუშაოები.

04
22 September -2024

B block

Land preparation works are underway in Block B.

05
09 September -2024

Partitions of the 7th floor

In block A, the work of removing the neighborhood partitions of the 7th floor is in progress.

06
23 August -2024

7th floor

In block А, the work of removing the neighborhood partitions of the 6th and 7th floors is in progress.

07
19 July -2024

Internal works

In Block А, the internal partitions on the 6th floor were completed and on the 7th floor, block piling of neighborhood walls is underway.

08
01 July -2024

12th floor

The roof tile of the 12th floor was completed. Block piling works for the facade and neighborhood walls are underway.

09
10 June -2024

The roof of the 11th floor

The roof tile of the 11th floor is completed in Ponichala.

10
24 May -2024

11th floor

The tile of the 11th floor is completed in Ponichala.

11
20 May -2024

10th floor

The columns of the 10th floor have been built, and preparatory works for covering the roof are underway. At the same time, the work of assembling the inner walls of the apartments on the 4th floor is going on.

12
07 May -2024

The roof of the 9th floor

The roof tile of the 9th floor is completed in Ponichala. At the same time, the works of piling the interior of the apartments from the 2nd to the 4th floor inclusive are going on.

13
22 April -2024

9th Floor

The arrangement of diaphragms for the column of the 9th floor has been completed, concrete will be poured today. At the same time, the works of assembling the facade radish on the inner and outer perimeter of the apartments on the 2-4 floors are going on.

14
01 April -2024

8th floor

The work of arranging the roof tile of the 8th floor is being completed. Also, on the second residential floor, the partition walls separating the outer facade and the inner apartments are being constructed.

15
18 January -2024

5th Floor

The 5th floor tile was poured on the ongoing construction in Ponichala.

16
24 December -2023

4th Floor

The 4th floor has been covered and the columns of the 5th floor are being built.

17
05 December -2023

4th Floor

The fourth floor columns and diaphragm arrangement works are underway.

18
03 November -2023

3rd Floor

Preparation works for the third floor columns have started in Ponichala.

19
10 October -2023

2nd Floor

In Ponichala, the laying of the 2nd floor slab has been completed. We are waiting for it to dry.

20
13 September -2023

Pouring concrete

Concrete works of commercial floor columns and diaphragms are underway in Ponichala.

21
31 August -2023

Commercial Floor

A commercial floor tile was poured in Ponichala during the construction of Solum Development.

22
08 August -2023

Overlapping

In Ponichala Roofing slabs for the parking floor are being arranged

23
12 July -2023

Concrete pouring

1400 cubic meters of concrete were poured in Ponichala.

24
29 June -2023

arrangement of fittings

The slab reinforcement of the object is being arranged. 152 tons of reinforcement were purchased.

25
03 June -2023

Perometer mold

In Ponichala, the works of arranging the base of the foundation slab and the external perometer mold have been completed.

26
06 May -2023

Foundation

In Ponichal project, the preparatory concrete layer works for the foundation have been completed. 100m3 of concrete was used.

27
04 April -2023

Land works

The construction of the new project of Solum Development has started in Ponichala. Earth removal works are in progress.