popup cover
Leave us a number 🚀
Our real estate expert will help you choose the apartment of your dreams💙
timeline 0 timeline 0 timeline 0 timeline 0
01
22 October -2025

3rd Floor Columns

Work on the project is actively underway - at this stage, the laying and pouring of columns on the 3rd floor (+7.50 mark) is being carried out.

3rd Floor Columns
timeline 1 timeline 1 timeline 1 timeline 1 timeline 1
02
08 October -2025

3rd Floor Tile

Within the framework of the project, the 3rd floor slab (+7.50 mark) was successfully poured. At this stage, the work of removing the columns is underway.  

3rd Floor Tile
timeline 2 timeline 2 timeline 2 timeline 2 timeline 2
03
27 September -2025

Roofing of the 2nd Floor

Within the framework of the project, the roofing slab of the 2nd floor (+4.30 mark) was successfully poured. With the above works, the monolithic construction of the 2nd floor has been completed, and preparatory works for the next floor have begun. Construction is underway according to the planned schedule and is being fully ensured in compliance with international quality standards.

Roofing of the 2nd Floor
timeline 3 timeline 3 timeline 3 timeline 3 timeline 3
04
15 September -2025

2nd floor

The work of laying the roofing slab of the 2nd floor (+4.30 mark) is underway.

2nd floor
timeline 4 timeline 4 timeline 4 timeline 4 timeline 4
05
27 August -2025

2nd floor columns

Work is underway to install column diaphragms on the 2nd floor (+4.30 mark).

2nd floor columns
timeline 5 timeline 5 timeline 5 timeline 5 timeline 5
06
12 August -2025

2nd floor

The work of pouring the slab of the 2nd floor (+4.30 mark) is underway.

2nd floor
timeline 6 timeline 6 timeline 6 timeline 6
07
23 July -2025

1st floor diaphragms

The work of pouring columns and diaphragms of the 1st floor (+0.00 mark) is underway.

1st floor diaphragms
timeline 7 timeline 7 timeline 7 timeline 7
08
07 July -2025

1st floor columns

Work is underway to lay the columns of the 1st floor (+0.00 mark) and prepare for pouring concrete.

1st floor columns
timeline 8 timeline 8 timeline 8
09
23 June -2025

1st floor roofing

The roofing of the 1st floor (+0.00 mark) has been completed and the second roofing slab has been poured.

1st floor roofing
timeline 9 timeline 9 timeline 9
10
13 June -2025

1st floor

The slab laying work on the 1st floor (+0.00 mark) has been completed.

1st floor
timeline 10 timeline 10 timeline 10
11
22 May -2025

-1st floor slab

The work of laying the roofing slab for the -1st floor (-2.9 mark) is underway.

-1st floor slab
timeline 11 timeline 11 timeline 11
12
05 May -2025

-1st floor

The removal of walls on the -1st floor (-2.9 mark) is underway - reinforcement is being laid and preparations are being made for pouring concrete.

-1st floor
timeline 12 timeline 12 timeline 12 timeline 12
13
25 April -2025

Pouring the foundation slab

Foundation slab pouring works are underway.

Pouring the foundation slab
timeline 13 timeline 13
14
07 April -2025

Foundation

Foundation work is underway, lay the reinforcement, and prepare for pouring concrete.

Foundation
timeline 14 timeline 14
15
26 March -2025

Foundation

Reinforcement laying and foundation preparation works are underway.

Foundation
timeline 15
16
05 March -2025

Ground preparation

Ground preparation is underway - digging and leveling the soil.

Ground preparation
timeline 16 timeline 16
17
17 February -2025

Land clearing

Land clearing works are underway in Gldani.

Land clearing
timeline 17 timeline 17 timeline 17 timeline 17 timeline 17
18
23 January -2025

Tower crane

Tower crane installation works are underway in Gldani.

Tower crane
timeline 18 timeline 18
19
18 December -2024

Preparatory work

The construction area is fenced. Concrete piers have been made near the one-story house and the foundation for the crane has been poured. (45 m³ of concrete)

Preparatory work