popup cover
en.dagvitove_nomeri_title
Our real estate expert will help you choose the apartment of your dreams💙
timeline 0 timeline 0 timeline 0
01
23 June -2025

1st floor roofing

The roofing of the 1st floor (+0.00 mark) has been completed and the second roofing slab has been poured.

1st floor roofing
timeline 1 timeline 1 timeline 1
02
13 June -2025

1st floor

The slab laying work on the 1st floor (+0.00 mark) has been completed.

1st floor
timeline 2 timeline 2 timeline 2
03
22 May -2025

-1st floor slab

The work of laying the roofing slab for the -1st floor (-2.9 mark) is underway.

-1st floor slab
timeline 3 timeline 3 timeline 3
04
05 May -2025

-1st floor

The removal of walls on the -1st floor (-2.9 mark) is underway - reinforcement is being laid and preparations are being made for pouring concrete.

-1st floor
timeline 4 timeline 4 timeline 4 timeline 4
05
25 April -2025

Pouring the foundation slab

Foundation slab pouring works are underway.

Pouring the foundation slab
timeline 5 timeline 5
06
07 April -2025

Foundation

Foundation work is underway, lay the reinforcement, and prepare for pouring concrete.

Foundation
timeline 6 timeline 6
07
26 March -2025

Foundation

Reinforcement laying and foundation preparation works are underway.

Foundation
timeline 7
08
05 March -2025

Ground preparation

Ground preparation is underway - digging and leveling the soil.

Ground preparation
timeline 8 timeline 8
09
17 February -2025

Land clearing

Land clearing works are underway in Gldani.

Land clearing
timeline 9 timeline 9 timeline 9 timeline 9 timeline 9
10
23 January -2025

Tower crane

Tower crane installation works are underway in Gldani.

Tower crane
timeline 10 timeline 10
11
18 December -2024

Preparatory work

The construction area is fenced. Concrete piers have been made near the one-story house and the foundation for the crane has been poured. (45 m³ of concrete)

Preparatory work