01
15 September -2025

Roofing of the 2nd floor

The work of laying the roofing slab of the 2nd floor (+4.30 mark) is underway.

Roofing of the 2nd floor
timeline 1 timeline 1 timeline 1 timeline 1 timeline 1
02
27 August -2025

2nd floor columns

Work is underway to install column diaphragms on the 2nd floor (+4.30 mark).

2nd floor columns
timeline 2 timeline 2 timeline 2 timeline 2 timeline 2
03
12 August -2025

2nd floor

The work of pouring the slab of the 2nd floor (+4.30 mark) is underway.

2nd floor
timeline 3 timeline 3 timeline 3 timeline 3
04
23 July -2025

1st floor diaphragms

The work of pouring columns and diaphragms of the 1st floor (+0.00 mark) is underway.

1st floor diaphragms
timeline 4 timeline 4 timeline 4 timeline 4
05
07 July -2025

1st floor columns

Work is underway to lay the columns of the 1st floor (+0.00 mark) and prepare for pouring concrete.

1st floor columns
timeline 5 timeline 5 timeline 5
06
23 June -2025

1st floor roofing

The roofing of the 1st floor (+0.00 mark) has been completed and the second roofing slab has been poured.

1st floor roofing
timeline 6 timeline 6 timeline 6
07
13 June -2025

1st floor

The slab laying work on the 1st floor (+0.00 mark) has been completed.

1st floor
timeline 7 timeline 7 timeline 7
08
22 May -2025

-1st floor slab

The work of laying the roofing slab for the -1st floor (-2.9 mark) is underway.

-1st floor slab
timeline 8 timeline 8 timeline 8
09
05 May -2025

-1st floor

The removal of walls on the -1st floor (-2.9 mark) is underway - reinforcement is being laid and preparations are being made for pouring concrete.

-1st floor
timeline 9 timeline 9 timeline 9 timeline 9
10
25 April -2025

Pouring the foundation slab

Foundation slab pouring works are underway.

Pouring the foundation slab
timeline 10 timeline 10
11
07 April -2025

Foundation

Foundation work is underway, lay the reinforcement, and prepare for pouring concrete.

Foundation
timeline 11 timeline 11
12
26 March -2025

Foundation

Reinforcement laying and foundation preparation works are underway.

Foundation
timeline 12
13
05 March -2025

Ground preparation

Ground preparation is underway - digging and leveling the soil.

Ground preparation
timeline 13 timeline 13
14
17 February -2025

Land clearing

Land clearing works are underway in Gldani.

Land clearing
timeline 14 timeline 14 timeline 14 timeline 14 timeline 14
15
23 January -2025

Tower crane

Tower crane installation works are underway in Gldani.

Tower crane
timeline 15 timeline 15
16
18 December -2024

Preparatory work

The construction area is fenced. Concrete piers have been made near the one-story house and the foundation for the crane has been poured. (45 m³ of concrete)

Preparatory work