|
20 December -2024 |
11th floor
Block A - Removal of internal partitions on the 11th floor; Block B - Removal of columns and pouring of concrete on the -1st floor is underway. |
Gallery
|
Gallery |
|
|
|
04 December -2024 |
-1st floor tile
Block A - The removal of internal and adjacent partitions on the 10th floor is underway. Installation of metal-plastic doors and windows has been completed up to and including the 5th floor; Block B - The slab of the 1st floor (1250 cubic meters of concrete) has been poured and floor leveling works are underway. |
Gallery
|
Gallery |
|
|
|
22 November -2024 |
10th floor
Block A - Removal of internal and adjacent partitions on the 10th floor; Block B - Second layer of reinforcement is being installed to begin pouring concrete into the foundation. |
Gallery
|
Gallery |
|
|
|
05 November -2024 |
The first layer of the foundation
Block A - removal of internal and neighboring partitions on the 8th and 9th floors is in progress; Block B - the foundation was placed on a rock mass, which is distinguished by its exceptional strength and seismic resistance. The first layer of the foundation has been poured, the reinforcement is being tied to pour the 2nd slab of the foundation. |
Gallery
|
Gallery |
|
|
|
23 October -2024 |
9th floor
Block A - the construction of the block on the 9th floor is in progress; Block B - ground cutting works are being completed. |
Gallery
|
Gallery |
|
|
|
09 October -2024 |
8th and 9th floor
А ბლოკი - მიმდინარეობს მე-8 და მე-9 სართულის სამეზობლო ტიხრების ამოყვანის სამუშაოები; B ბლოკი - მიმდინარეობს კატლავანის ამოღების სამუშაოები. |
Gallery
|
Gallery |
|
|
|
22 September -2024 |
B block
Land preparation works are underway in Block B. |
Gallery
|
Gallery |
|
|
|
09 September -2024 |
Partitions of the 7th floor
In block A, the work of removing the neighborhood partitions of the 7th floor is in progress. |
Gallery
|
Gallery |
|
|
|
23 August -2024 |
7th floor
In block А, the work of removing the neighborhood partitions of the 6th and 7th floors is in progress. |
Gallery
|
Gallery |
|
|
|
19 July -2024 |
Internal works
In Block А, the internal partitions on the 6th floor were completed and on the 7th floor, block piling of neighborhood walls is underway. |
Gallery
|
Gallery |
|
|
|
01 July -2024 |
12th floor
The roof tile of the 12th floor was completed. Block piling works for the facade and neighborhood walls are underway. |
Gallery
|
Gallery |
|
|
|
10 June -2024 |
The roof of the 11th floor
The roof tile of the 11th floor is completed in Ponichala. |
Gallery
|
Gallery |
|
|
|
24 May -2024 |
11th floorThe tile of the 11th floor is completed in Ponichala. |
Gallery
|
Gallery |
|
|
|
20 May -2024 |
10th floorThe columns of the 10th floor have been built, and preparatory works for covering the roof are underway. At the same time, the work of assembling the inner walls of the apartments on the 4th floor is going on. |
Gallery
|
Gallery |
|
|
|
07 May -2024 |
The roof of the 9th floor
The roof tile of the 9th floor is completed in Ponichala. At the same time, the works of piling the interior of the apartments from the 2nd to the 4th floor inclusive are going on. |
Gallery
|
Gallery |
|
|
|
22 April -2024 |
9th FloorThe arrangement of diaphragms for the column of the 9th floor has been completed, concrete will be poured today. At the same time, the works of assembling the facade radish on the inner and outer perimeter of the apartments on the 2-4 floors are going on. |
Gallery
|
Gallery |
|
|
|
01 April -2024 |
8th floorThe work of arranging the roof tile of the 8th floor is being completed. Also, on the second residential floor, the partition walls separating the outer facade and the inner apartments are being constructed. |
Gallery
|
Gallery |
|
|
|
18 January -2024 |
5th FloorThe 5th floor tile was poured on the ongoing construction in Ponichala. |
Gallery
|
Gallery |
|
|
|
24 December -2023 |
4th FloorThe 4th floor has been covered and the columns of the 5th floor are being built. |
Gallery
|
Gallery |
|
|
|
05 December -2023 |
4th FloorThe fourth floor columns and diaphragm arrangement works are underway. |
Gallery
|
Gallery |
|
|
|
03 November -2023 |
3rd FloorPreparation works for the third floor columns have started in Ponichala. |
Gallery
|
Gallery |
|
|
|
10 October -2023 |
2nd FloorIn Ponichala, the laying of the 2nd floor slab has been completed. We are waiting for it to dry. |
Gallery
|
Gallery |
|
|
|
13 September -2023 |
Pouring concreteConcrete works of commercial floor columns and diaphragms are underway in Ponichala. |
Gallery
|
Gallery |
|
|
|
31 August -2023 |
Commercial FloorA commercial floor tile was poured in Ponichala during the construction of Solum Development. |
Gallery
|
Gallery |
|
|
|
08 August -2023 |
OverlappingIn Ponichala Roofing slabs for the parking floor are being arranged |
Gallery
|
Gallery |
|
|
|
12 July -2023 |
Concrete pouring1400 cubic meters of concrete were poured in Ponichala. |
Gallery
|
Gallery |
|
|
|
29 June -2023 |
arrangement of fittingsThe slab reinforcement of the object is being arranged. 152 tons of reinforcement were purchased. |
Gallery
|
Gallery |
|
|
|
03 June -2023 |
Perometer moldIn Ponichala, the works of arranging the base of the foundation slab and the external perometer mold have been completed. |
Gallery
|
Gallery |
|
|
|
06 May -2023 |
FoundationIn Ponichal project, the preparatory concrete layer works for the foundation have been completed. 100m3 of concrete was used. |
Gallery
|
Gallery |
|
|
|
04 April -2023 |
Land worksThe construction of the new project of Solum Development has started in Ponichala. Earth removal works are in progress. |
Gallery
|
Gallery |
|