Construction Process
![]() ![]() ![]() ![]() |
22 October -2025 |
3rd Floor Columns
Work on the project is actively underway - at this stage, the laying and pouring of columns on the 3rd floor (+7.50 mark) is being carried out. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() ![]() ![]() ![]() |
08 October -2025 |
3rd Floor Tile
Within the framework of the project, the 3rd floor slab (+7.50 mark) was successfully poured. At this stage, the work of removing the columns is underway. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() ![]() ![]() ![]() |
27 September -2025 |
Roofing of the 2nd Floor
Within the framework of the project, the roofing slab of the 2nd floor (+4.30 mark) was successfully poured. With the above works, the monolithic construction of the 2nd floor has been completed, and preparatory works for the next floor have begun. Construction is underway according to the planned schedule and is being fully ensured in compliance with international quality standards. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() ![]() ![]() ![]() |
15 September -2025 |
2nd floor
The work of laying the roofing slab of the 2nd floor (+4.30 mark) is underway. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() ![]() ![]() ![]() |
27 August -2025 |
2nd floor columns
Work is underway to install column diaphragms on the 2nd floor (+4.30 mark). |
![]() |
Gallery
|
Gallery |
|
![]() ![]() ![]() ![]() ![]() |
12 August -2025 |
2nd floor
The work of pouring the slab of the 2nd floor (+4.30 mark) is underway. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() ![]() ![]() |
23 July -2025 |
1st floor diaphragms
The work of pouring columns and diaphragms of the 1st floor (+0.00 mark) is underway. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() ![]() ![]() |
07 July -2025 |
1st floor columns
Work is underway to lay the columns of the 1st floor (+0.00 mark) and prepare for pouring concrete. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() ![]() |
23 June -2025 |
1st floor roofing
The roofing of the 1st floor (+0.00 mark) has been completed and the second roofing slab has been poured. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() ![]() |
13 June -2025 |
1st floor
The slab laying work on the 1st floor (+0.00 mark) has been completed. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() ![]() |
22 May -2025 |
-1st floor slab
The work of laying the roofing slab for the -1st floor (-2.9 mark) is underway. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() ![]() |
05 May -2025 |
-1st floor
The removal of walls on the -1st floor (-2.9 mark) is underway - reinforcement is being laid and preparations are being made for pouring concrete. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() ![]() ![]() |
25 April -2025 |
Pouring the foundation slab
Foundation slab pouring works are underway. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() |
07 April -2025 |
Foundation
Foundation work is underway, lay the reinforcement, and prepare for pouring concrete. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() |
26 March -2025 |
Foundation
Reinforcement laying and foundation preparation works are underway. |
![]() |
Gallery
|
Gallery |
|
![]() |
05 March -2025 |
Ground preparation
Ground preparation is underway - digging and leveling the soil. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() |
17 February -2025 |
Land clearing
Land clearing works are underway in Gldani. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() ![]() ![]() ![]() |
23 January -2025 |
Tower crane
Tower crane installation works are underway in Gldani. |
![]() |
Gallery
|
Gallery |
|
![]() ![]() |
18 December -2024 |
Preparatory work
The construction area is fenced. Concrete piers have been made near the one-story house and the foundation for the crane has been poured. (45 m³ of concrete) |
![]() |
Gallery
|
Gallery |
|