Building process

  • 23. 01. 2023

    Commercial roofing

    Roofing slabs of the commercial floor of Block A are in progress
  • 19. 12. 2022

    Columns

    In block A, the columns and walls of the commercial floor were poured. In block B, the construction of the columns of the commercial floor is in progress.
  • 31. 10. 2022

    Commercial floor

    In block A, the laying of the slab of the commercial floor is in progress, and in block B, the laying of the column of the 0th floor is in progress.
  • 08. 10. 2022

    Block A

    The walls of the underground floor of block A were poured. In the next week, the waterproofing of the walls will be arranged and the earth will be backfilled into the foundation
  • 03. 10. 2022

    Walls

    Foundation walls and columns are made on block A Reinforced concrete slab, reinforced concrete basement walls and diaphragms are poured on block B.
  • 21. 09. 2022

    Underground Floor

    The foundation slab of block A is poured. on 440m2. The walls of the underground floor of Block B are poured. By the end of the month, it is planned to pour the walls of the underground floor of block A and waterproof the outer perimeter of its walls.
  • 01. 09. 2022

    walls and columns

    In block A, the foundation slab is being prepared, and in block B, reinforced concrete walls and columns are being built.
  • 16. 08. 2022

    The foundation laid

    The foundation of block B was laid. 80 cm thick at the -3.00 mark. We are starting to arrange the walls and roofing structures of the underground floor. as well as reinforcement of the foundation of block A.
  • 02. 08. 2022

    Foundation

    At this stage, the reinforcement of the foundation slab is underway
  • 15. 07. 2022

    Land works

    Construction has started in Avchala, and at this stage, land is being cut for the foundation.
  • 03. 01. 1970

    Preparation

    The surrounding area is being rehabilitated and preparations are underway for the ground works